Change Orders 101: What Every Developer Should Know Before Ground Breaks

Change orders aren't a sign something went wrong. Not understanding how yours will be priced and approved is.

September 4, 2026

Construction site change order review
Nearly All

Construction projects generate at least one change order

5 to 15%

Commonly cited cost impact range across the industry

Before You Sign

The only time to set your change order process on your terms

C hange orders are a normal part of construction, not a red flag on their own. Site conditions differ from what a soil report predicted. An owner decides mid-project that a unit mix should change. A jurisdiction updates a code requirement after permits are already pulled. None of that means the contractor did anything wrong.

What separates a manageable change order process from an expensive one isn't whether change orders happen. It's whether the pricing, approval, and documentation process was defined before the first one showed up.

Most developers only think hard about change orders after they've received one they didn't expect. This guide is meant to get you thinking about it earlier than that.

A change order isn't the problem. An undefined change order process is.

Where Change Orders Come From

What Actually Triggers One

Most change orders fall into one of a small number of categories. Knowing which one you're looking at changes how you should respond to it.

01

Differing site conditions

Unexpected soil, rock, groundwater, or existing utilities not shown on the drawings. This is the category most likely to be genuinely unavoidable, and the one your contract's differing-conditions clause should already address.

02

Owner-directed changes

A decision to change unit mix, finishes, or layout after design is locked. These are the most controllable category, since they originate with you, not the site or the code.

03

Code or jurisdiction changes

A building department updates a requirement between permit submission and inspection, or interprets an existing code differently than expected. Rare, but worth asking your GC how they've handled it before.

04

Design errors or omissions

Something missing or incorrect in the construction documents themselves. Who bears this cost, the design team, the GC, or you, should already be addressed in your contracts before it comes up.

If your GC can't tell you which category a change order falls into, that's worth pausing on. The category should shape who pays and how it's priced.

How It Gets Priced

Pricing & Approval

This is where most disputes actually start, not over whether a change order is legitimate, but over how much it costs and who signed off on it.

05

Unit pricing vs. time and materials

Unit pricing, an agreed rate per square foot or per fixture, is far easier to verify than open-ended time and materials billing. Push for unit pricing wherever the scope allows it.

06

Markup transparency

Get the markup percentage on labor and materials in writing before you sign the original contract, not when the first change order lands. Renegotiating markup mid-project is a much weaker position to negotiate from.

07

Written approval before work begins

Work should not start on a change order before you've approved a price in writing. If it already has, you've lost most of your ability to negotiate that price down.

Set This Up Early

Protecting Yourself

Every protection here has to be in place before you sign the original contract. None of it works retroactively.

08

Get the process in writing, not just the markup

Who submits a change order, how fast you're required to respond, and what happens if you don't respond, all of it should be spelled out in the contract, not handled informally as it comes up.

09

Track cumulative cost, not just each change order in isolation

A single change order might look small. Ten of them against a fixed budget add up fast. Keep a running total against your contingency line from day one.

10

Ask how your GC has handled disagreements over change orders before

Every GC has had a change order dispute at some point. How they describe handling it tells you more about them than a reference call about a project that went smoothly.

If a GC resists writing any of this down before you sign, treat that the same way you'd treat resistance on any other contract term. It's a preview of how they'll handle it mid-project.

Before You Sign

Change orders aren't something you can eliminate. What you can control is whether the process for handling them is clear, in writing, and agreed to before the first one shows up. That single decision, made before ground breaks, does more to protect your budget than almost anything else in the contract.